NEW QUESTION 12
Identify the three sources from which supply chain orchestration (SCO) can create the work orders.

  • A. Procurement
  • B. Inventory Min-Max Planning
  • C. Planning
  • D. Order Management
  • E. Quality

Answer: A,C,D

 

NEW QUESTION 13
Identify the two configurations in Supply Chain cloud applications of Product Information Management (PIM) and Order promising (GOP), which must be set to process the Back-to-Back order with Make Supply Order, for a nonstocked item.

  • A. Set the nonstocked item to be back-to-back enabled in Product Information Management (PIM).
  • B. Set the global sourcing rule in GOP to determine supply creation option as Make.
  • C. Create Supply Chain Orchestration Supply Execution Document Creation Rule for the nonstocked item.
  • D. Set a local sourcing rule in GOP to determine supply creation option as Make.
  • E. Create Supply Order Orchestration Defaulting and Enrichment Rule for the nonstocked item.

Answer: A,B

 

NEW QUESTION 14
As part of an implementation project, you have to perform setups related to a Manufacturing plant in Functional Setup Manager.
What must be set up first in order for you to configure the setup task called Manage Plant Parameters?

  • A. The Manufacturing Master Data Functional Area
  • B. The Manage Items Profile Options tasks
  • C. The Manage product and Child Value Sets task
  • D. The Supply Chain Orchestration Functional Area

Answer: A

 

NEW QUESTION 15
Identify four parameters that are considered in the calculation of manufacturing lead time in Oracle Manufacturing Cloud.

  • A. Resource calendars of the work centers involved
  • B. Resource calendar exceptions
  • C. The shifts are defined in the plant calendar
  • D. Plant calendar exceptions
  • E. The primary work definition of the item
  • F. The lot size of the item

Answer: B,C,E,F

 

NEW QUESTION 16
The production user wants to report Work Order completion.
Identify two ways of reporting the progress of work order at work order operation level.

  • A. Complete using quantity completion
  • B. Change Move status to Ready.
  • C. Quick Complete
  • D. Change status of Operation to completed
  • E. Complete with Details

Answer: C,E

 

NEW QUESTION 17
A Manufacturing Engineer in a plant is creating an alternative manufacturing process for an item using its existing Work Definitions. After copying from the existing Work Definition WD1 to the alternative Work Definition WD2, the engineer finds that the operation items were not copied in the alternative manufacturing process WD2.
Identify the reason.

  • A. The Item and Structure Name were changed in the new Work Definition WD2 during creation.
  • B. The Start Data was not populated in the new Work Definition WD2 during creation.
  • C. The Item and Structure Name in the existing Work Definition WD1 were retained in the new Work Definition WD2 as well during creation.
  • D. The Production Priority was not populated in the new Work Definition WD2 during creation.

Answer: B

 

NEW QUESTION 18
Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.

  • A. Rescheduled Work Order WO-2045 duration = 3.25days
  • B. Rescheduled Work Order WO-2045 duration = 1.25 days
  • C. Rescheduled Work Order WO-2045 duration = 0.75 days
  • D. Rescheduled Work Order WO-2045 duration = 2 days

Answer: C

 

NEW QUESTION 19
Your customer has multiple distribution centers and a few manufacturing plants. Plants make different items with some overlap between them in terms of products manufactured. The distribution centers stock parts from all plants. A Corporate Engineering team is responsible for centrally defining items and catalogues. This team defines the items and sets the attributes for most parameters. The respective distribution centers and manufacturing plants are allowed to change some attributes locally.
Identify two different ways of achieving this requirement.

  • A. Set up Plants as Inventory Organizations, Distribution Centers as Item Organizations, and Corporate Engineering organization as Inventory Organization.
  • B. Set up Plants as Inventory Organizations, Distribution Centers as Inventory Organizations, and Corporate Engineering organizations as Item Organization.
  • C. Set up Plants and Distribution Centers as Inventory organizations and Corporate Engineering organization as Inventory Organization.
  • D. Set up Plants as Inventory Organizations, Distribution Centers as Item Organizations, and Corporate Engineering organization as Item Organization.
  • E. Set up Plants and Distribution Centers as Inventory organizations and Corporate Engineering organization as Item Organization

Answer: B,E

 

NEW QUESTION 20
Your customer has the following business requirement. There are two work definitions created in the application. One Work Definition for Engine Finished Good and other Work Definition for Pallet Finished Good. The Engine Finished Good item should have Pallet Finished Goods as one of its component.
Identify the way to establish the relationship between Pallet and Engine Work Definitions.

  • A. Create a Subinventory that could be the completion Subinventory for yielding the pallet and then the same Subinventory can serve as the supply Subinventory of the pallet in the Work Definition created for Engine.
  • B. The two Work Definitions can be tied through Project or Seiban numbers.
  • C. The Work Definition versions can be used to tie the Work Orders.
  • D. Assign a higher priority to the Work Definition created for Engine and a lower one for the Work Definition for Pallet.

Answer: C

 

NEW QUESTION 21
Your customer has completed the required setup steps for automatic work definition. Identify the option that shows the navigation steps needed to create an automatic work definition.

  • A. Manufacturing > Work Definition> Manage Standard Operations> Create automatic definition
  • B. Manufacturing> Work Definition> Manage Standard Operations> Select default standard operation> Actions> Create automatic work definition
  • C. Product Management> Product Information Management> Items> Edit Item > Actions> Create automatic work definition
  • D. Manufacturing > Work Definition> Manage Work Definitions> Actions> Create automatic work definition

Answer: B

 

NEW QUESTION 22
In your customer's manufacturing facility, different types of Movement Requests are created. Key manufacturing components are issued to the work orders form the manufacturing subinventory. The manufacturing subinventory receives its supplies form the Warehouse subinventory through automatically created Movement Requests.
Which type of Movement Requests should you use to fill the manufacturing subinventory form the Warehouse subinventory?

  • A. Batch Wave Movement Requests
  • B. Requisition Movement Requests
  • C. Replenishment Requests
  • D. Pick Wave Movement Requests

Answer: B

 

NEW QUESTION 23
During a Manufacturing Cloud implementation, the customer request to develop Oracle Transactional Business Intelligence reports that are not available out-of- the box.
Identify the tool that is available to the Report Developer in Manufacturing Cloud to develop the reports.

  • A. Oracle Business Intelligence Standard Edition
  • B. Oracle Business Intelligence Application
  • C. Oracle Business Intelligence Publisher
  • D. Oracle Business Intelligence Enterprise Edition

Answer: C

 

NEW QUESTION 24
Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A resource LATHE is assigned to the work center W1. There are five units of LATHE available, of which three units are available for the Morning Shift and the remaining units are available for the Evening Shits.
Which two actions must you perform to associate LATHE with W1?

  • A. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 40% against the resource LATHE in the Evening Shift column.
  • B. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 3 against the resource LATHE in the Morning Shift column.
  • C. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 60% against the resource LATHE in the Morning Shift column.
  • D. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 2 against the resource LATHE in the Evening Shift column.
  • E. Select the Available 24 Hours check box and in the Resource Availability region, enter 2 against the resource LATHE in the Evening Shift column.
  • F. Select the Available 24 Hours check box and in the Resource Availability region, enter 3 against the resource LATHE in the Morning Shift column.

Answer: C,F

 

NEW QUESTION 25
A user wants to transfer the work order status updates and resource transaction data for costed resources to Cost Management.
Which scheduled process should you run to achieve this requirement?

  • A. Transfer General Ledger Balances to Balance Cubes
  • B. Transfer Ledger Balances
  • C. Transfer Transactions to Costing
  • D. Transfer Cost to Cost Management

Answer: D

 

NEW QUESTION 26
An order entry specialist creates a Back-to-Back order for product item with an intention of fulfilling by in-house manufacturing. The fulfillment line is scheduled and Supply Chain Orchestration (SCO) has initiated creation of a Supply Order rather than Work Order.
Identify two options that can cause this situation.

  • A. Sourcing rules for the product item are defined as Make as well as Transfer.
  • B. Sourcing rules for the product item are defined as Buy as well as Transfer.
  • C. Sourcing rule for the product item is defined as Buy.
  • D. Sourcing rule for the product item is defined as Make, but Work Definition is not defined.

Answer: A,D

 

NEW QUESTION 27
Your customer plans to use Oracle Representational State Transfer (REST) API with Oracle Supply Chain Management Cloud (Oracle SCM Cloud) to support integration requirements.
Identify four REST resources and the corresponding HTTP action available with Manufacturing Cloud.

  • A. Work Order Status POST method
  • B. Work Order Status GET method
  • C. Work Orders GET method
  • D. Resource transaction GET method
  • E. Work Orders PATCH method
  • F. Resource transaction POST method

Answer: B,C,E,F

 

NEW QUESTION 28
You are in the process of defining a Standard Operation for visual inspection. You want the completion of this standard operation to be reported in all work orders that reference it.
Identify the setup that will fulfill this requirement.

  • A. Select the Automatically Transact check box while defining the Standard Operation.
  • B. Ensure that the Charge Type of the resource is Automatic.
  • C. Select the Count Point check box while defining the Standard Operation.
  • D. Deselect the Count Point check box while defining the Standard Operation.

Answer: C

 

NEW QUESTION 29
Identify three entities that must be set up in Oracle Manufacturing Cloud to create a Work Definition for an item that will be manufactured in-house.

  • A. Resources
  • B. Production Line
  • C. Operation Items
  • D. Manufacturing Lead Time
  • E. Operations

Answer: A,C,E

 

NEW QUESTION 30
Identify the three changes that are allowed to be made to active Work Definition in a Work Center, without creating a new version.

  • A. Add an Operation
  • B. Costing Priority
  • C. Delete an Operation
  • D. Completion Subinventory
  • E. Production Priority

Answer: A,D,E

 

NEW QUESTION 31
To reduce the subassembly stock with no impact on material planning of child components of the subassemblies stock, you need to modify the multilevel item structure of a product.
Identify the action that meets this requirement.

  • A. Change the Supply Type = Phantom in Item definition and Work Definition, for subassemblies having high inventory stock.
  • B. Change the Supply Type = Assembly Pull in Item definition and Work Definition, for subassemblies having high inventory stock.
  • C. Change the Supply Type = Operation Pull in Item definition and Work Definition, for subassemblies having high inventory stock.
  • D. Change the Supply Type = Push in Item definition and Work Definition, for subassemblies having high inventory stock.

Answer: B

 

NEW QUESTION 32
The Cost Accountant has reported to the Production Supervisor that the Work Order transactions are not getting transferred to Costing.
Identify the reason for work order transactions not getting transferred to Costing.

  • A. The item was made inactive after the Work Order transaction.
  • B. The Costing Interfaced Attribute is not enabled in the resource definition.
  • C. The Costing Interfaced Attribute is enabled in the resource definition.
  • D. The Manage Item Rules setup is not complete.

Answer: B

 

NEW QUESTION 33
In what three ways can you set the overcompletion tolerance for a subcomponent yield, so the job order can report the excess production completion?

  • A. Overcompletion Tolerance Type = Percentage, value > 0
  • B. Overcompletion Tolerance Type = Amount, value > 0
  • C. Overcompletion Tolerance Type = Amount, value = 0
  • D. Overcompletion Tolerance Type = Percentage, value = 0
  • E. Overcompletion Tolerance Type = Percentage, value = 100

Answer: A,C,D

 

NEW QUESTION 34
In a Manufacturing Cloud post production support environment, a user wants to update some of the operations in the work orders by using the Midpoint Scheduling feature. However, the user is unable to update any of the orders.
Identify two reasons.

  • A. The operations are missing sequence.
  • B. The scheduled resources are not part of the organization selected by the user.
  • C. None of the operations include scheduled resources.
  • D. The work order operations do not have operations start or completion date.

Answer: A,C

 

NEW QUESTION 35
......